CAT 2022 Slot 3 QA · Question 16

A group of people worked on a project. They finished of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of is

  1. A.
    23
  2. B.
    140
  3. C.
    36
  4. D.
    150