CAT 2021 Slot 1 QA · Question 12

Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is

Type-in answer (TITA): no options, no negative marking.

Sign in free to see the answer and the step-by-step solution.